Drumkeeran Church Renovations
Week 1
Starting Monday, 8 June.
(View Progress for Other Weeks)
Work began with the erection of the scaffolding.
![](renov01_b.jpg)
![](renov01_c.jpg)
Friday, 12 June
![](renov02_a.jpg)
![](renov02_b.jpg)
![](renov02_c.jpg)
Old slates are removed from the side-aisle roof and insulation is installed
![](renov02_d.jpg)
Old slates being removed from the roof over the Sacristy.
![](renov02_e.jpg)
Scaffolding on the gable end nears completion